Ongoing2026

Fiberisation of 9 segments, MamujuMamuju

Aerial fiber optic routes, 9 segments in the Mamuju area, West Sulawesi. About 59 km of new cable with more than 800 new poles, including one 4-segment ring of about 36 km. Work started in mid-October 2026, with completion targeted for mid-December 2026.

Region
South Sulawesi
Location
Mamuju
Type of work
Fiber rollout
Volume
9 segments
Client segment
ISP
Year
2026
Progress
13%

Scope of work

  • Mobilisation of teams, tools, HSE and PPE
  • New 7 m and 9 m steel poles, including coordinate tagging
  • Slack hanger installation
  • Aerial fiber optic cable pulling, including anti-rodent cable
  • HDPE and riser pipe installation
  • Cable labelling
  • Site finishing and patch cords