Completed2024
Rail corridor fiber backbone restoration, 8 segmentsSidoarjo – Porong – Bangil – Sukorejo – Lawang
Restoration of a fiber optic backbone along the rail corridor in 8 segments: Sidoarjo – Tanggulangin, three Porong – Bangil segments, Bangil – Sukorejo, and Lawang. The work covered new poles, cable pulling, splicing into the existing network, and end-to-end OTDR testing through to handover.
- Region
- East Java
- Location
- Sidoarjo – Porong – Bangil – Sukorejo – Lawang
- Type of work
- Restoration
- Volume
- 40 km
- Client segment
- Network provider
- Year
- 2024
Scope of work
- Foundations dug and cast for approx. 830 poles
- Approx. 40 km of 48-core fiber cable pulled
- Bridge hanging
- Splicing into the existing network at handholes
- Tracing and repair of break points with jumper cables
- End-to-end OTDR testing and handover