Ongoing2026

Inter-site links in North Lombok, 7 segmentsNorth Lombok

Inter-site fiber optic links in North Lombok Regency: 7 segments in a single ring topology from Klui to Sesait Kayangan. About 107 km of new cable in total, with more than 1,600 new poles. The work is scheduled for 60 calendar days from late September 2026.

Region
Bali and West Nusa Tenggara
Location
North Lombok
Type of work
Inter-site links
Volume
7 segments
Client segment
ISP
Year
2026
Progress
18%

Scope of work

  • New 7 m and 9 m poles
  • Aerial fiber optic cable pulling
  • Cable hangers and HDPE subduct
  • Core splicing at closures, ODPs and OTBs
  • Labelling of cables, joint closures, ODPs and OTBs
  • Site finishing, patch cords and handover

Other projects

Similar work

All projects